Describe the issue or problem
A completed review still shows as “Request Resent / Awaiting response” in the editor’s workflow after the reviewer was reinstated. The review was actually submitted, but the editor cannot read or confirm it.

Steps I took leading up to the issue

  1. A reviewer’s request was cancelled (review deadline passed).
  2. In Workflow → Review → Reviewers, I used ⋯ → Reinstate Reviewer (Resend Review Request).
  3. The reviewer logged in, accepted and submitted the review.

What I expected to happen
The reviewer’s status should change to “Complete”, and the editor should be able to read and confirm the review.

What actually happened

  • The Activity Log shows: “[Reviewer] has completed the review for the round 1 review for submission 50”, and the “Review complete” email was sent.
  • The reviewer’s own dashboard lists the assignment under “Completed”.
  • In the editor’s workflow and dashboard, the reviewer still shows “Request Resent / Awaiting response”, with only “Edit Due Date” and “Unassign” available.
  • I have cleared the data and template caches, and there are no failed jobs.

Application version
OJS 3.5.0.5

Question
Is this a known issue, and is there a safe way to correct the review assignment status without losing the submitted review?